march, second half

(work the second hull, all operations have been covered in photos of the first)

Sun, 16-Mar-03 Assemble bulkheads in hullskins, epoxy keel joint

Mon, 17-Mar-03 Epoxy bulkhead fillets (part 1)

Tue, 18-Mar-03 Epoxy bulkhead fillets (part 2)

Wed, 19-Mar-03 Start on beambox components

Thu, 20-Mar-03 Beambox components

Fri, 21-Mar-03 Beambox components

Sat, 22-Mar-03 Beambox components

Sun, 23-Mar-03 Two coats of epoxy to inner hullskins and bulkheads. Epoxy beamboxes in place

Tue, 25-Mar-03 Start to fit insulation board (buoyancy) in fore and aft compartments, stringers

Wed, 26-Mar-03 Cutting buoyancy to size, supports for pintles, chainplates etc

Thu, 27-Mar-03 Epoxy stringers and various supports in place

Fri, 28-Mar-03 Shaping gunwhales

Sat, 29-Mar-03 Shaping gunwhales, cut decks to rough size

Sun, 30-Mar-03 Two coats of epoxy to inner face of decks

Mon, 31-Mar-03 Pre-fit decks

What's next? April!