(work the second hull, all operations have been covered in photos of the first)
Sun, 16-Mar-03 Assemble bulkheads in hullskins, epoxy keel joint
Mon, 17-Mar-03 Epoxy bulkhead fillets (part 1)
Tue, 18-Mar-03 Epoxy bulkhead fillets (part 2)
Wed, 19-Mar-03 Start on beambox components
Thu, 20-Mar-03 Beambox components
Fri, 21-Mar-03 Beambox components
Sat, 22-Mar-03 Beambox components
Sun, 23-Mar-03 Two coats of epoxy to inner hullskins and bulkheads. Epoxy beamboxes in place
Tue, 25-Mar-03 Start to fit insulation board (buoyancy) in fore and aft compartments, stringers
Wed, 26-Mar-03 Cutting buoyancy to size, supports for pintles, chainplates etc
Thu, 27-Mar-03 Epoxy stringers and various supports in place
Fri, 28-Mar-03 Shaping gunwhales
Sat, 29-Mar-03 Shaping gunwhales, cut decks to rough size
Sun, 30-Mar-03 Two coats of epoxy to inner face of decks
Mon, 31-Mar-03 Pre-fit decks
What's next? April!